Friday, March 23, 2012

Progress Update

Kick off reviewed questions from IT staff and client.
Forward cabling and infrastructure quote to client.
Cabling vendor estimated to start Feb. 21st.
AV vendor working on design of classrooms.
Coordination meeting setup for March 5th for relocating the clients.
Updated issues log.

Next two weeks
Site walkthroughs.
Follow up with Comcast on TV cable install.
Follow up on core and conduit from IDF.
Follow up with cabling installation.
Review issues log.

Thursday, March 1, 2012

Progress Update

GBTC WDCE Renovation project 3rd and 4th floor
• Kick off reviewed questions from IT staff and client.
• Forward cabling and infrastructure quote to client.
• Cabling vendor estimated to start Feb. 21st.
• AV vendor working on design of classrooms.
• Coordination meeting setup for March 5th for moving relocating the clients.
• Updated issues log.
• Update @Task and Blog

Next two weeks
• Site walkthroughs.
• Follow up with Comcast on TV cable install.
• Follow up on core and conduit from IDF.
• Follow up with cabling installation.
• Review issues log.

Friday, February 3, 2012

Progress Update

• Kick off reviewed questions from IT staff and client.
• Forward cabling and infrastructure quote to client.
• Comcast meeting on site scheduled for February 8th.
• AV vendor working on design of classrooms.

Friday, January 13, 2012

Progress Update

Received design of future 3rd floor renovation
Site walkthrough 3r fl Dec 8th with client, vendor, and IT groups
Third floor design review on Dec 8th.
Sent quote to client on Dec 18th for 3rd floor cabling quote
Preparing questions from IT groups for client since this is a remote site
Follow up with client on estimated construction start date