Friday, March 23, 2012

Progress Update

Kick off reviewed questions from IT staff and client.
Forward cabling and infrastructure quote to client.
Cabling vendor estimated to start Feb. 21st.
AV vendor working on design of classrooms.
Coordination meeting setup for March 5th for relocating the clients.
Updated issues log.

Next two weeks
Site walkthroughs.
Follow up with Comcast on TV cable install.
Follow up on core and conduit from IDF.
Follow up with cabling installation.
Review issues log.

Thursday, March 1, 2012

Progress Update

GBTC WDCE Renovation project 3rd and 4th floor
• Kick off reviewed questions from IT staff and client.
• Forward cabling and infrastructure quote to client.
• Cabling vendor estimated to start Feb. 21st.
• AV vendor working on design of classrooms.
• Coordination meeting setup for March 5th for moving relocating the clients.
• Updated issues log.
• Update @Task and Blog

Next two weeks
• Site walkthroughs.
• Follow up with Comcast on TV cable install.
• Follow up on core and conduit from IDF.
• Follow up with cabling installation.
• Review issues log.